Dimension IV reported to the Village Board this past Monday evening on progress that was being made in developing the bid plans and specifications for the new Municipal Facility. We are on track to let the bids in early January. Architect Dan Roarty reviewed choices for the front facade options and decorative lighting.
Staff updated the board on the design of the technology systems that will be included in the building including security systems, audio visual systems for the board and committee rooms, telephone system and the computer networking. The Village is working with Remote Operations Company, 200 Packerland Drive in the design of these systems.
The next scheduled update on the facility will be on January 4 at 7 PM during the regular Board Meeting.
Wednesday, December 23, 2009
Thursday, December 10, 2009
Report From Monday, December 7, 2009
The Village Board reviewed a number of the design elements that will be used at the new Municipal Service Center. They reviewed designs for the entrance area, decorative lighting, garage doors and interior lighting styles. The board also reviewed the future door types, and partition specifications for the Board Room area. This partition will allow the new board room to be divided to be used for two meetings instead of just one.
The bid for the construction of the two service roads into the property was awarded to McKeefrey & Sons, Inc. in the amount of $17,730. These roads will allow access to the property in the spring for building construction.
The board also approved hiring a consultant to prepare a report on the technology needs of the new facility and integration into our current set-up. The successful bidder will prepare a report to the board on the technology needs of the building, current technology that may be considered and provide the construction drawings needed to prepare the facility to accept the needed technology hook-ups. After board review, a bid for the equipment and installation will be issue based on the recommendations.
The next update on the facility will be held on December 21st, as a part of the regular board meeting, at 7PM.
The bid for the construction of the two service roads into the property was awarded to McKeefrey & Sons, Inc. in the amount of $17,730. These roads will allow access to the property in the spring for building construction.
The board also approved hiring a consultant to prepare a report on the technology needs of the new facility and integration into our current set-up. The successful bidder will prepare a report to the board on the technology needs of the building, current technology that may be considered and provide the construction drawings needed to prepare the facility to accept the needed technology hook-ups. After board review, a bid for the equipment and installation will be issue based on the recommendations.
The next update on the facility will be held on December 21st, as a part of the regular board meeting, at 7PM.